Bags of Concrete per Cubic Yard, Explained

The per-yard bag counts people quote — 45, 60, or 90 — come from dividing 27 cubic feet by a typical bag yield. This page shows that arithmetic, the limits of the assumption, and how a waste allowance changes the count.

The usual rule of thumb

One cubic yard is 27 cubic feet. If an 80 lb bag is taken to yield about 0.60 cubic feet, then 27 ÷ 0.60 = 45 bags per cubic yard. A 60 lb bag at about 0.45 cubic feet is 27 ÷ 0.45 = 60 bags per cubic yard. A 40 lb bag at about 0.30 cubic feet is 27 ÷ 0.30 = 90 bags per cubic yard. Those three yields are the typical planning figures used across this site. They are not guaranteed: the same nominal bag weight from two brands can list different yields, and the yield can change with water content and how the mix is placed.

Bag size (US premix)Typical yield assumed hereBags per cubic yard (27 ÷ yield)
80 lb0.60 cu ft45
60 lb0.45 cu ft60
40 lb0.30 cu ft90

Waste, and when ready-mix is simpler

A 5–10% waste allowance is common for cutting, over-excavation, uneven subgrade, and spillage. On a full cubic yard, 10% waste raises an 80 lb count from 45 bags to 50 bags (45 × 1.10 = 49.5, rounded up). For larger pours, ready-mix is often ordered in 0.25 cubic yard increments and is usually more practical than stacking tens of bags.

Worked slab example: 10 ft × 10 ft × 4 in = 33.33 cu ft = 1.235 cu yd. Bags at the 80 lb yield, with no waste: 33.33 ÷ 0.60 = 55.6, rounded up to 56 bags. With 10% waste: 36.67 ÷ 0.60 = 61.1, rounded up to 62 bags. Use the bag calculator to change the dimensions, the waste percentage, or the yield.

Metric bags

In the UK and much of the EU, bagged concrete is commonly sold in 20 kg or 25 kg bags. This site’s default planning yields are 0.0125 m³ per 25 kg bag and 0.010 m³ per 20 kg bag. At those assumptions, one cubic meter is about 80 bags of 25 kg, or 100 bags of 20 kg, before waste. Again, read the bag: “concrete mix,” “ballast,” and “cement” are not the same product (see the cement calculator).

Assumptions used on this site (typical planning figures; always confirm the product you buy): 1 cubic yard = 27 cubic feet. Thickness in inches is converted to feet (divide by 12) before multiplying. Typical premix bag yields: 80 lb ≈ 0.60 cu ft (~45 bags/yd³), 60 lb ≈ 0.45 cu ft (~60 bags/yd³), 40 lb ≈ 0.30 cu ft (~90 bags/yd³). A 5–10% waste allowance is common. Ready-mix is often ordered in 0.25 yard increments. Metric bag yields, when used: 25 kg ≈ 0.0125 m³ and 20 kg ≈ 0.010 m³, unless you enter the yield from the bag.

Disclaimer: These tools give planning estimates only. Bag yields vary by brand and mix, so check the coverage printed on the bag you buy. Ready-mix quantities, slump, reinforcement, and thickness for any structural, load-bearing, frost-protected, or code-regulated work must follow the project specification, the adopted local building code, and the judgment of a qualified professional. This site is not a structural design service and does not replace a licensed engineer or contractor.